The Main Benefit of Story Points

On This Page

Get Free Estimating Book Chapters!

Get Free Estimating Book Chapters!

Please provide your name and email and we’ll send you the sample chapters and we’ll send a short weekly tip from Mike on how to succeed with agile.

Get my chapters now!

If story points are an estimate of the time (effort) involved in doing something, why not just estimate directly in hours or days? Why use points at all?

There are multiple good reasons to estimate product backlog items in story points, and I cover them fully in the Agile Estimating and Planning video course, but there is one compelling reason that on its own is enough to justify the use of points.

It has to do with King Henry I who reigned between 1100 and 1135. Prior to his reign, a “yard” was a unit of measure from a person’s nose to his outstretched thumb. Just imagine all the confusion this caused with that distance being different for each person.

King Henry eventually decided a yard would always be the distance between the king’s nose and outstretched thumb. Convenient for him, but also convenient for everyone else because there was now a standard unit of measure.

You might learn that for you, a yard (as defined by the king’s arm) was a little more or less than your arm. I’d learn the same about my arm. And we’d all have a common unit of measure.

Story points are much the same. Like English yards, they allow team members with different skill levels to communicate about and agree on an estimate. As an example, imagine you and I decide to go for a run. I like to run but am very slow. You, on the other hand, are a very fast runner. You point to a trail and say, “Let’s run that trail. It’ll take 30 minutes.”

I am familiar with that trail, but being a much slower runner than you, I know it takes me 60 minutes every time I run that trail. And I tell you I’ll run that trail with you but that will take 60 minutes.

And so we argue. “30.” “60.” “30.” “60.”

We’re getting nowhere. Perhaps we compromise and call it 45 minutes. But that is possibly the worst thing we could do. We now have an estimate that is no good for either of us.

So instead of compromising on 45, we continue arguing. “30.” “60.” “30.” “60.”

Eventually you say to me, “Mike, it’s a 5-mile trail. I can run it in 30 minutes.”

And I tell you, “I agree: it’s a 5-mile trail. That takes me 60 minutes.”

The problem is that we are both right. You really can run it in 30 minutes, and it really will take me 60. When we try to put a time estimate on running this trail, we find we can’t because we work (run) at different speeds.

But, when we use a more abstract measure—in this case, miles—we can agree. You and I agree the trail is 5 miles. We just differ in how long it will take each of us to run it.

Story points serve much the same purpose. They allow individuals with differing skill sets and speeds of working to agree. Instead of a fast and slow runner, consider two programmers of differing productivity.

Like the runners, these two programmers may agree that a given user story is 5 points (rather than 5 miles). The faster programmer may be thinking it’s easy and only a day of work. The slower programmer may be thinking it will take two days of work. But they can agree to call it 5 points, as the number of points assigned to the first story is fairly arbitrary.

What’s important is once they agree that the first story is 5 points, our two programmers can then agree on subsequent estimates. If the fast programmer thinks a new user story will take two days (twice his estimate for the 5-point story), he will estimate the new story as 10 points. So will the second programmer if she thinks it will take four days (twice as long as her estimate for the 5-point story).

And so, just as runners can agree on the relative effort required to run the same trail, Agile teams can use story points to align their estimates even if they might complete that work at different rates.

Mike Cohn

About the Author

Mike Cohn specializes in helping companies adopt and improve their use of agile processes and techniques to build extremely high-performance teams. He is the author of User Stories Applied for Agile Software Development, Agile Estimating and Planning, and Succeeding with Agile as well as the Better User Stories video course. Mike is a founding member of the Agile Alliance and Scrum Alliance and can be reached at hello@mountaingoatsoftware.com. If you want to succeed with agile, you can also have Mike email you a short tip each week.